Milestones in Structural and Timber Construction
Several trades are working simultaneously on the construction site: While the special foundation work is nearing successful completion, the installation of precast concrete elements is in full swing. A large portion of these massive elements was installed on schedule by the end of 2025. At the same time, timber construction also gained significant momentum. The defined goal: By Christmas 2025, the majority of the roof structure over the high-bay warehouse and the shuttle area should be completed.