THE CONSTRUCTION OF THE NEW DM DISTRIBUTION CENTER IS CREATING A LANDMARK BUILDING THAT WILL SET NEW STANDARDS FOR EFFICIENT AND SUSTAINABLE LOGISTICS. IN IMPLEMENTING THIS MAJOR PROJECT, SWIETELSKY IS DRAWING ON ITS MANY YEARS OF EXPERIENCE IN DEVELOPING CHALLENGING BUILDING CONSTRUCTION PROJECTS.

251123 Dm Verteilzentrum AT (C)SWIETELSKY (2)

Milestones in Structural and Timber Construction

Several trades are working simultaneously on the construction site: While the special foundation work is nearing successful completion, the installation of precast concrete elements is in full swing. A large portion of these massive elements was installed on schedule by the end of 2025. At the same time, timber construction also gained significant momentum. The defined goal: By Christmas 2025, the majority of the roof structure over the high-bay warehouse and the shuttle area should be completed.

251123 Dm Verteilzentrum AT (C)SWIETELSKY (3)

Progress on the Parking Deck, Basement Levels, and Infrastructure

Visible progress is also emerging across the other construction phases. On the parking deck, the final concrete work was underway at the same time and was likewise scheduled for on-time completion by the end of 2025. In addition, all basement levels of the structure will be structurally completed before the end of this year. Another major step for the technical infrastructure was imminent: the installation work for the power supply ring circuit.

251123 Dm Verteilzentrum AT (C)SWIETELSKY (6)

An Overview of the Next Construction Phases

Looking ahead to further project steps, the next phases have already been defined and, in part, already carried out:

· Mid-February 2026: Erection of the timber load-bearing structure for the wide-aisle warehouse

· Spring 2026: Start of work on the first sections of the monolithic floor slabs

· March 2028: Scheduled overall completion of the dm distribution center

Project Profile

· Project: dm Distribution Center

· Location: Kronstorf, Upper Austria

· Duration: May 2025 to May 2028

· Planning: Österreich Mitte

· Services: Logistics │ Concrete │ Timber Construction

· Characteristics: Maximum capacity scenario of 552 trips per day │ Initial operation at a maximum of 150 trips or 75 trucks per day │ Distance to the B 309: approx. 600 meters as the crow flies