Complex Construction Phase and Demanding Substructure Engineering
The execution of the project posed significant structural and logistical challenges for the construction team. The tight site footprint in the heart of the city required meticulous coordination. The building was constructed as a solid structure using in-situ (cast-in-place) concrete combined with semi-precast elements, including the use of semi-precast components for the basement transfer slab ("Sargdeckel"). A major logistical achievement was also the positioning and operation of the tower crane directly inside the inner courtyard.
The construction of the two-level underground car park required a complex excavation shoring system, implemented using sheet pile walls, secant bored pile walls, as well as stabilizing steel walers and steel beams. To reliably manage groundwater conditions, the substructure was executed as a "white tank" system (Weiße Wanne – water-impermeable concrete) to ensure structural waterproofing against hydrostatic water pressure. This was supplemented by a continuous dewatering system, where groundwater was drained in a controlled manner via two dedicated seepage/infiltration wells established along the site perimeter.