Installation of Crane Runway Rails at the Vienna South Freight Center

260601 Kranbahnschienenverlegung Güterzentrum AT (C)SWIETELSKY (11)

THE VIENNA SOUTH FREIGHT CENTER TERMINAL IS A TECHNICAL MASTERPIECE IN WHICH SWIETELSKY DEMONSTRATES THE HIGHEST LEVEL OF PRECISION. OVER A TOTAL LENGTH OF 763 METERS AND WITH A CRANE TRACK WIDTH OF 44 METERS, APPROXIMATELY 10,400 DRILL HOLES ARE BEING DRILLED BY HAND. A TESTAMENT TO TECHNICAL EXPERTISE AND THE HIGHEST QUALITY.

260601 Kranbahnschienenverlegung Güterzentrum AT (C)SWIETELSKY (3)

Utmost precision and 10,400 drill holes in the foundation

Behind this technical masterpiece lies precise manual and skilled labor. To securely anchor the massive AS86 crane rails with BG 15/40 fasteners at 60-centimeter intervals to the concrete pedestals, approximately 10,400 holes were drilled by hand into the reinforced concrete foundation. Despite this enormous effort, the well-coordinated team accurately installs and pours 120 meters of rail every day.

260601 Kranbahnschienenverlegung Güterzentrum AT (C)SWIETELSKY (1)

Welding and Profiling Under Extreme Conditions

The temperature-dependent linear expansion of the 760-millimeter crane runway rail poses a particular technical challenge. This is addressed through a special machining process applied to the weld joints on the solid crane rail (Type AS86). Under difficult, hard-to-reach conditions, the rails must be precisely profiled not only at the rail head but also at the weld root (at the rail foot).

260601 Kranbahnschienenverlegung Güterzentrum AT (C)SWIETELSKY (12)

Well-Coordinated Synergies and Extensive Use of Machinery

This major project benefits from the team’s collaboration and specialized machinery:

· The turnouts were transported directly to the installation site on turnout transport cars (WTW) and laid on-site using a railway slewing crane (EDK)

· Track laying was performed partly by machine using the rapid-conversion train (SUZ 500) and partly by hand using dual-mode excavators

· For final completion, a GW-MDZ tamps both the switches and the tracks to their final elevation and alignment

Project Profile

· Project: Crane runway rail installation

· Location: Vienna South

· Responsibility: Bahnbau Österreich

· Services: Switch installation │ Track construction │ GW-MDZ │ Fleet support │ Specialized equipment │ Rail alignment at a rate of 120 meters per day

· Characteristics: 763 meters total length │ 44 meters crane track width │ Precision work │ 10,400 manual drill holes │ Temperature-dependent linear expansion