Customized Adaptation to the Subsoil
For the construction of the new tree islands, the “Sponge City” system was adapted to local conditions and the existing subsoil conditions. The new tree sites were constructed to a depth of approximately 130 cm to provide the trees with the necessary foundation for long-term healthy growth.
Technical Layer Structure of the Tree Islands
The construction of the tree islands follows a precise, multi-stage layer structure:
· Water distribution: A ring-shaped drainage system was installed in each planting island to ensure targeted water distribution.
· Structural substrate: Installation of 60 cm of structural substrate consisting of 32/36 crushed granite enriched with 15% by volume of composted charcoal.
· Aeration system: Tree aeration is ensured in two ways. On the one hand, through the large pores of the structural substrate; on the other hand, via a perforated pipe system
· Substrates in the topsoil layer: A root-permeable tree substrate compliant with FLL standards was installed in the upper layer
· Targeted irrigation: A custom-built irrigation system ensures a reliable water supply to the trees during the establishment phase