IN THE HISTORIC TOWN OF HALLSTATT, THE CONSTRUCTION OF THE NEW SALZBERGBAHN IS A TECHNICALLY CHALLENGING CONSTRUCTION PROJECT. HTB IS UNDERTAKING THE STRUCTURALLY CHALLENGING SPECIAL CIVIL ENGINEERING WORK ON EXTREMELY STEEP TERRAIN.
The focus is on creating a safe and permanently stable foundation for the new Salzbergbahn. To reliably meet the tight schedule leading up to the planned opening, HTB is relying on its own strong team of up to 30 employees, specialized equipment for rock drilling, and precisely coordinated alpine construction site logistics.
Foundation Work on Extremely Steep Terrain
The core of the construction project involves the construction of a total of 38 foundation sites, each of which will be built with two individual foundations. Since some of the sites are located on extremely steep terrain and directly against rock faces, precise expertise in specialized civil engineering is required. Depending on the prevailing soil conditions, the foundations will either be deep-set on micropiles or anchored directly into the rock to ensure the long-term stability of the new railway.
Alpine Construction Site Logistics
Logistical operations in alpine terrain pose a major challenge, as conventional construction vehicles cannot access the individual construction sections. Material transport therefore takes place primarily via two temporarily installed material cableways. Helicopter support is additionally utilized, particularly in hard-to-reach sections.
Powerful Specialized Equipment and In-House Expert Personnel
Specialized equipment is used for the demanding rock drilling work, including up to three walking excavators operating simultaneously, mounted drill rigs, as well as small and hand-held drilling rigs. A key factor in the project’s success is the well-coordinated HTB team. Up to 30 employees are on site during peak periods. This allows all work to be coordinated flexibly without the need for subcontractors.
Project Profile
· Project: New construction of the Salzbergbahn
· Location: Hallstatt, Upper Austria
· Duration: 2025 to 2026
· Responsibility: Österreich West │ HTB
· Services: 3 walking excavators │ Mounted drilling rigs │ Small and hand-held drilling equipment │ 2 temporary material cableways │ Helicopter flights
· Features: 38 foundation sites, each with two individual foundations │ Structural engineering expertise