Schneeberg Railway, Lower Austria

WITH THE RENOVATION OF THE TRACK SYSTEM ON THE HOCHSCHNEEBERG, A TECHNICALLY AND LOGISTICALLY CHALLENGING CONSTRUCTION PROJECT IN AN ALPINE SETTING WAS SUCCESSFULLY COMPLETED. SWIETELSKY DEMONSTRATES WHAT IS POSSIBLE THROUGH ITS COMMITMENT, STRONG TEAMWORK, AND TECHNICAL AND LOGISTICAL EXPERTISE.

At an elevation of nearly 1,800 meters, the project demanded total commitment: All construction site logistics had to be handled exclusively by rail, while cramped conditions, technical failures, and a late onset of winter required the utmost flexibility and precision craftsmanship.

Xx Schneebergbahn AT (C)SWIETELSKY (5)

Railway Construction at High Altitudes in the Alps

The conditions at the Hochschneeberg made it clear that this was no ordinary construction site. At an elevation of 1,600 to 1,800 meters above sea level, the work spanned a route length of approximately 570 meters, divided into two tunnels and an open-air section in between. Supplies could be delivered exclusively by rail via the rack-and-pinion railway and mine cars. In addition to the cramped conditions and the challenging tunnel sections, the extreme weather conditions on the mountain placed high demands on both people and equipment. As part of the project, major sections of track were replaced, rack rails were installed, and the infrastructure in the construction area was sustainably modernized.

Xx Schneebergbahn AT (C)SWIETELSKY (11)

Craftsmanship and Excellence in the Face of Machine Failure

The project’s challenges became evident during unforeseen incidents on site. While work was underway, the tamping machine broke down. The team reacted immediately: what had originally been planned to be done by machine was quickly reworked and carried out manually with great craftsmanship. A total of 42 anchors were installed through painstaking manual labor, representing a remarkable achievement by the team and ensuring continuous construction progress.

Xx Schneebergbahn AT (C)SWIETELSKY (8) (1)

Late Winter Storm and Final Night Shifts

Toward the end of construction, the Hochschneeberg once again revealed its rugged alpine side. A sudden, late winter storm caused snow to blow deep into the tunnel. Despite these extreme conditions, the team completed the project quickly. The final welding work was carried out in just a few night shifts, enabling the entire project to be successfully completed.

Project Profile

· Project: Renovation of the rack-and-pinion track system

· Location: Hochschneeberg, Lower Austria

· Responsibility: Bahnbau Ost at the Fischamend site

· Scope of Work: Track renewal with rack-and-pinion drive │ Manual installation of anchors │ Welding work

· Characteristics: Elevation of 1,600 to 1,800 meters │ Track length of approximately 570 meters │ Supply of materials and site logistics