Precise Logistics on the Move
The track renewal work was carried out in two phases. During the first phase, the teams replaced rails, ties, and other track components along a section of track approximately 40 kilometers long.
The work was supported by the SMD80 track renewal machine from SWIETELSKY’s fleet, which carried out the continuous replacement of rails and ties. To reliably maintain international rail traffic to Austria, continuous track access had to be interrupted and restarted several times.