Track Replacement on the Czech-Austrian Railroad Line, Austria/Czech Republic

260613 Tschechisch Österreichische Eisenbahnverbindung AT (C)SWIETELSKY (1)

SWIETELSKY IS CARRYING OUT A CHALLENGING TRACK RENOVATION ON THE MOST IMPORTANT CZECH-AUSTRIAN RAILWAY CONNECTION, WHICH RUNS BETWEEN ČESKÉ BUDĚJOVICE IN SOUTH BOHEMIA AND SUMMERAU IN AUSTRIA. SIWETELSKY CARRIED OUT A CYCLICAL RENOVATION OF THE RAILWAY INFRASTRUCTURE ON THE SECTION BETWEEN VČELNÁ AND HORNÍ DVOŘIŠTĚ.

The project has a clear goal: a sustainably upgraded rail infrastructure lays the foundation for safe, more reliable, and seamless rail traffic on this heavily trafficked European rail line.

260613 Tschechisch Österreichische Eisenbahnverbindung AT (C)SWIETELSKY (9)

Precise Logistics on the Move

The track renewal work was carried out in two phases. During the first phase, the teams replaced rails, ties, and other track components along a section of track approximately 40 kilometers long.

The work was supported by the SMD80 track renewal machine from SWIETELSKY’s fleet, which carried out the continuous replacement of rails and ties. To reliably maintain international rail traffic to Austria, continuous track access had to be interrupted and restarted several times.

260613 Tschechisch Österreichische Eisenbahnverbindung AT (C)SWIETELSKY (3)

Mechanized Track Bed Cleaning and Completion

In May 2026, the second construction phase began, with the goal of final completion. The scope of work included mechanized ballast cleaning of the track bed, the replacement of worn-out ties, the installation of new rails, and the improvement of drainage systems. In total, approximately 30 kilometers of track were newly laid and 25,000 ties were replaced throughout the entire project.

260613 Tschechisch Österreichische Eisenbahnverbindung AT (C)SWIETELSKY (7)

Work Beyond the Open Track

The modernization extended far beyond the open track and included key engineering structures and transportation hubs:

· Seven railroad crossings were completely rebuilt along the corridor.

· A bridge structure on the section between Kaplice and Velešín was repaired.

· Track construction work took place at various junctions along the route, including in Včelná, Holkov, and Kaplice.

260613 Tschechisch Österreichische Eisenbahnverbindung AT (C)SWIETELSKY (4)

Technical and Organizational Expertise

The successful implementation of this rail corridor demonstrates the teams’ ability to manage challenging rail construction projects on time and safely under tight operational schedules. The result is a high-performance rail infrastructure for international passenger and freight traffic between South Bohemia and Austria.

Project Profile

· Project: Včelná–Horní Dvořiště section

· Location: between České Budějovice (Czech Republic) and Summerau (Austria)

· Duration: through 2026

· Responsibility: Bahnbau International Ost

· Scope of Work: Track construction │ SMD80 track renewal machine │ Track bed & drainage │ Reconstruction of 7 railroad crossings │ Repair of a bridge structure

·         Specifications:  30 km of track │ 25,000 ties │ one bridge structure